Sunday, April 30, 2006

By the way



























We had a ceremonial "Signing of the Site" where we left our mark for all time. It was pretty cool.
Of course we had to pose for a picture!

That is a mighty green door. It's that color both outside and inside. None of us know why.

Week of April 24th




Here are some photos of the job site at the beginning of the week...
















Now that everyone is caught up with the progress of the house visually, I can tell you what is going on.


The front and back porches are finished, as is the siding of the house. (Because of siding complications, siding of the garage could not be completed)

The dry wall is completely painted! We had started to paint the dry wall last week, and it was finished over the course of the week.
Now all that is really left is the installation of the kitchen cabinets (as seen above), door placement (most are in place already actually, molding (again, pretty much finished), and carpet (not finished at all).

Good times.

Wednesday, April 19, 2006

Week of April 10, 2006



Good day. This week on site was fairly productive considering most of the house is "finished".

Our class returned from spring break to see that the dry wall, and the siding was already in place. The front and back porches were also in nice shape, just needing a little paint. Overall, it looked pretty solid.

Most of the class painted the front and back porches, while some sided the house and garage.






Justin, doing his stuff


Paint crew, word


Don't fall JJ!

Sunday, April 09, 2006

April 8th, 06

Andrea and I went out on site today with the help of my dog, Bailee. We worked alongside Mel and Mike. There were quite a few college kids who came out from OSU to help, along with the family. We finished most of the siding on the garage, we would have done more, but we ran out of siding. The drywall inside the house was finished up by a group of the college kids. In the end, the house is turning out to look pretty good.

Heather Meena

Friday, April 07, 2006

Week of April 3, 2006


Not on site this week because of spring break.

The Saturday crews, Tuesday and Thursday crews hung the drywall.