We worked on siding the garage and the site was graded with earth moving machines.










Andrea operates a skid steer loader with scoop bucket.

Friday, March 17, 2006

Week of March 13, 2006

Ohio Graduation Tests this week which meant that our classes were shortened so we could not go to site.

Monday, March 13, 2006

Saturday, March 11, 2006

No work on site today - rain.

Week of February 27, 2006

The garage siding was started and the sheathing on the roof was finished. The back porch trusses were cut apart and fixed on our truss day by the females and the entire back porch roof is now theirs to build.














Saturday, February 25, 2006


The rest of the trusses were installed today and the garage was prepped for starting the siding.